Under construction

SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR BMahaRERA P51600033475

by SUN INFRASTRUCTURES PVT LTD

145/1/145/3/149/1/149/2/151/152/1/155/2 HISSA No. 1, UPPER SAVARKAR NAGAR, GANGAPUR ROAD, NASHIK, 422013

Oct 2027
Possession
9.1%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jul 2024, now proposed Oct 2027 per the RERA filing.

Official RERA facts

Registration
P51600033475
Status
New
Stage
Certificate Signed
Possession
October 2027originally July 2024
Construction
9.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths10%
Storm Water Drains10%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station10%
Aggregate area of recreational Open Space10%
Open Parking10%

Building & registration

RERA registered
Feb 2022
Floors
4

Buyer community

Connect with other buyers and owners of SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.