Possession
55.5%
Built
0
Complaints
66
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 55.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P51600034088
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
55.5% complete
Units sold
46 of 66

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2022
Floors
10
Unit mix
56 res ยท 10 comm
Plot / CTS / survey no.
304 1 B Plot No 1 2 3
Planning authority
Nashik Municipal Corporation Nashik
Approved layout land
1,384 sq.m
Land for this registration
1,384 sq.m
Permissible built-up area
5,021.7 sq.m
Registered office
Amibansi Height
Plot boundaries
North
Plot No 6 and 7
South
24 Meter Road
East
Plot No 4
West
9 Meter Colony Road
Parking
163 four-wheeler32 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • HDFC BANK โ€” 51975
    IFSC HDFC0003669
    Raje Arcade Opp Hotel Excellency Inn Ambad Link Road Nashik

Commencement Certificate documents

  • Commencement Certificate_11zon.pdf

Buyer community

Connect with other buyers and owners of Kamdhenu Sky โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kamdhenu Sky. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.