PropPin
All RERA projects
🏗️
Under construction

TREELAND PHASE-5MahaRERA P51600034430

by ABH DEVELOPERS PRIVATE LIMITED

HISSA NO-5,6 AND 9, OF S NO 21/1 AND 3, 24, 25/1 AND 25/2, 167, 28/1/2/1, 28/1/2/2, AND 26/1, GANGAPUR ROAD, 422025

Dec 2026
Possession
61.4%
Built
0
Complaints
126
Units
High risk
  • Mortgaged to a lender (₹100 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹100 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51600034430
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
61.4% complete
Units sold
110 of 126

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Mortgaged to a lender

MahaRERA's financial encumbrance declaration shows this project has ₹100 Cr secured against a lender. If the promoter defaults, the lender's claim can outrank a buyer's — worth raising with the builder before booking.

Landowner

DINESH KANAYALAL MANWANI, VINOD KANAYALAL MANWANI, AREEHANT DEVELOPERS

Possession extension history

  • EA31122519189Revised to December 2026

    • Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work. • Slow progress of certain activities: Social distancing protocols and safety measures have inevitably slowed down the pace of certain construction tasks. • Suspension of the works: Temporary halts in construction activities due to government directives and safety precautions have interrupted the project’s continuity. • Delay in the supply of material and equipment: Disruption in the supply chain caused by lockdowns and logistical challenges have hindered the timely delivery of crucial material and equipment. • Delay related to the mobilization skilled labour and/or subcontractor’s resources: Mobilizing personnel and subcontractors amidst travel restrictions and health concerns has proven to be challenging. • Reduced efficiency of contractor’s staff due to remote working: Transitioning to remote work arrangements has impacted the efficiency and productivity of our workforce, leading to productivity losses. • Delays in contractor’s payments: Financial strains experienced by stakeholders in the wake of the pandemic have resulted in delays in payments, affecting project timelines.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildings90%
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposal60%
Water conservation /Rain water harvesting90%
Energy managemcnt60%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%
Open Parking60%

Building & registration

RERA registered
Apr 2022
Floors
26
Unit mix
126 res · 0 comm
Architect
UMESH BAGUL
Plot / CTS / survey no.
HISSA NO-5,6 AND 9, OF S NO 21/1 AND 3, 24, 25/1 AND 25/2, 167, 28/1/2/1, 28/1/2/2, AND 26/1
Planning authority
Others
Approved layout land
7,630.89 sq.m
Land for this registration
7,630.89 sq.m
Permissible built-up area
21,038 sq.m
Registered office
ABH TREELAND
Plot boundaries
North
ADJ GODA PARK
South
30 WIDE DP ROAD
East
--
West
ADJ SURVEY NO 21
Parking

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • HDFC BANK — 49569
    IFSC HDFC0001246
    SHOP NO 1, GROUND FLOOR, SUYOJIT SANKUL, TILAKWADI, SHARANPUR ROAD, NASHIK 422002

Commencement Certificate documents

  • TREELAND- COMMENCEMENT CERTIFICATE-Revised.pdf
  • COMMENCEMENT CERTIFICATE- 28-04-2023_compressed.pdf

Buyer community

Connect with other buyers and owners of TREELAND PHASE-5 — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching TREELAND PHASE-5. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.