PropPin
All RERA projects
🏗️
Under construction

THE CHOUPAALMahaRERA P51600034715

by KALANTRI AND BANG PROPERTIES

PLOT NO. 19 TO 22/1, 19 TO 22/2, 19 TO 22/3 AND 19 TO 22/4 OF S. NO. 602/A/1 TO 4/3/4/20 TO 23 F.P. NO. 135, 136 (P), 137 TPS NO. II OF NASHIK SHIWAR, NASHIK, TIDKE COLONY, NASHIK, 422002

Mar 2027
Possession
80.5%
Built
0
Complaints
185
Units
High risk
  • Mortgaged to a lender (₹22 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹22 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51600034715
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
80.5% complete
Units sold
71 of 185

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Mortgaged to a lender

MahaRERA's financial encumbrance declaration shows this project has ₹22 Cr secured against a lender. If the promoter defaults, the lender's claim can outrank a buyer's — worth raising with the builder before booking.

Possession extension history

  • EA28012619611Revised to March 2027

    During the relevant construction period, the project site experienced an abnormally early onset of monsoon commencing from April/May 2025, followed by prolonged and intense rainfall. Such unusual weather conditions severely affected construction activities, particularly excavation, RCC works, masonry, plastering and other external and weather-dependent works, which could not be carried out safely or efficiently. The early and prolonged monsoon conditions resulted in a significant shortage of labour, as frequent and continuous rainfall caused irregular attendance and reduced availability of the workforce. Despite the Promoter’s continuous efforts to retain labour and mobilize additional manpower, the availability of skilled and unskilled labour remained inconsistent, thereby adversely affecting the pace of construction. The cumulative impact of the above factors caused unavoidable disruption to the scheduled construction timeline. The delay is neither intentional nor due to any negligence or wilful default on the part of the Promoter. The Promoter assures MahaRERA that construction activities have resumed at full pace upon normalization of conditions, and the project shall be completed within the extended period sought.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water30%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting70%
Energy managemcnt50%
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Apr 2022
Floors
10
Unit mix
0 res · 185 comm
Architect
AR SANJAY M PATIL
Plot / CTS / survey no.
PLOT NO. 19 TO 22/1, 19 TO 22/2, 19 TO 22/3 AND 19 TO 22/4 OF S. NO. 602/A/1 TO 4/3/4/20 TO 23 F.P. NO. 135, 136 (P), 137 TPS NO. II OF NASHIK SHIWAR, NASHIK
Planning authority
NASHIK MUNICIPAL CORPORTATION
Approved layout land
5,140.5 sq.m
Land for this registration
5,140.5 sq.m
Permissible built-up area
21,531.18 sq.m
Registered office
PLOT NO. 06
Plot boundaries
North
602 - 1 TO 4 - 2
South
9 MTR COLONY ROAD
East
OPEN SPACE AREA
West
24 MTR DP ROAD
Parking
290 four-wheeler775 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • SARASWAT COOPERATIVE BANK LIMITED — 143179
    IFSC SRCB0000084
    SHARANPUR ROAD

Commencement Certificate documents

  • Commencement Certificate.pdf

Buyer community

Connect with other buyers and owners of THE CHOUPAAL — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching THE CHOUPAAL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.