Aditi ResidencyMahaRERA P51600045416

by Bhoomi Enterprises

Plot no 12+13,S.no/G.no.23/3/A of Kamathwade Shivar Nasik, Near Vikhepatil School, Nashik, 422008

Oct 2024
Possession
63.2%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Oct 2024) has passed with construction at 63.2%.

Official RERA facts

Registration
P51600045416
Status
New
Stage
Certificate Signed
Possession
October 2024
Construction
63.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Landowner

Mrs.jayashri Deepak Pawar

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
May 2022
Floors
6
Plot / CTS / survey no.
Plot no 12+13,S.no/G.no.23/3/A of Kamathwade Shivar Nasik
Planning authority
Others
Approved layout land
638.75 sq.m
Land for this registration
638.75 sq.m
Permissible built-up area
1,645.69 sq.m
Registered office
Mauli Sadan Apartment
Plot boundaries
North
Plot no 11
South
18 Meter Road
East
Plot no 14 and 15
West
9 Meter colony road
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • ICICI BANK LIMITED โ€” 68189
    IFSC ICIC0007497
    Ground Floor Shop No 4 Survey No 28 Qubism Pipe Line Road Anandvali Gangapur Road Nashik 422013

Commencement Certificate documents

  • COMMENCEMENT CERTIFICATE _compressed.pdf

Buyer community

Connect with other buyers and owners of Aditi Residency โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aditi Residency. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.