PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Mirage TowerMahaRERA P51600046828

by UNITY CONSTRUCTIONS

Plot No. 3+5, Survey No. 862/8, Nashik, 422006

Dec 2025
Possession
72.7%
Built
0
Complaints
52
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 72.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P51600046828
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
72.7% complete
Units sold
32 of 52

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2022
Floors
9
Unit mix
39 res ยท 13 comm
Architect
Kapil Thakkar
Plot / CTS / survey no.
Plot No. 3+5, Survey No. 862/8
Planning authority
Nashik Municipal Corporation
Approved layout land
933.5 sq.m
Land for this registration
933.5 sq.m
Permissible built-up area
3,773.43 sq.m
Registered office
Sunshine Residency B
Plot boundaries
North
Plot No 2 and 6
South
Plot No 4
East
6 Meter Wide Road
West
18 Meter Road
Parking
26 four-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • ICICI BANK LIMITED โ€” 63827
    IFSC ICIC0001868
    Bodhale Nagar Nashik

Commencement Certificate documents

  • Unity Commencement (1).pdf

Buyer community

Connect with other buyers and owners of Mirage Tower โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Mirage Tower. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.