Under construction

GANESH AARAMBHMahaRERA P51600047860

by NERKAR PROPERTIES LLP

SURVEY NO 184, NASHIK, 422213

Feb 2027
Possession
28.2%
Built
0
Complaints
0
Units
Caution
  • Behind schedule. Possession is due Feb 2027 but construction is only at 28.2%.

Official RERA facts

Registration
P51600047860
Status
New
Stage
Certificate Signed
Possession
February 2027
Construction
28.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Nov 2022
Floors
8
Plot / CTS / survey no.
SURVEY NO 184
Planning authority
Others
Approved layout land
4,707.92 sq.m
Land for this registration
4,707.92 sq.m
Permissible built-up area
16,948.51 sq.m
Registered office
RUSHIRAJ HEIGHTS
Plot boundaries
North
ADJ GAT NO 185
South
9 METER ROAD
East
ADJ GAT NO 184 2
West
ADJ GAT NO 183

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • BANK OF MAHARASHTRA โ€” 91139
    IFSC MAHB0001143
    CHINTAMAN GANGAPUR ROAD TATTE NAGAR NASHIK

Commencement Certificate documents

  • 1 Commencement Certificates _ NA Order for plotted development.pdf

Buyer community

Connect with other buyers and owners of GANESH AARAMBH โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GANESH AARAMBH. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.