DREAM PARADISEMahaRERA P51600049492

by RAGHUKUL BUILDCON

PLOT NO 3 & 4, GAT NO 110, NASHIK, 422010

Dec 2026
Possession
35.9%
Built
0
Complaints
0
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 35.9%.

Official RERA facts

Registration
P51600049492
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
35.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

RAGHUKUL BUILDCON

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Feb 2023
Floors
14
Plot / CTS / survey no.
PLOT NO 3 & 4, GAT NO 110
Planning authority
Others
Approved layout land
1,264.75 sq.m
Land for this registration
1,264.75 sq.m
Permissible built-up area
3,094.36 sq.m
Registered office
VAASTU NIRMAN
Plot boundaries
North
30MTR D P ROAD
South
COLONY ROAD
East
PLOT NO 5
West
COLONY ROAD
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • HDFC BANK โ€” 56388
    IFSC HDFC0009220
    ASMITA BUSINESS CENTRE, GROUND FLOOR PLOT NO 19 BEHIND PAPAYA NURSERY SATPUR COLONY NASHIK 422007

Commencement Certificate documents

  • 07COMMENCEMENTCERT.pdf

Buyer community

Connect with other buyers and owners of DREAM PARADISE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DREAM PARADISE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.