PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Laxminarayan HarmonyMahaRERA P51600049671

by Laxminarayan Developers

Plot No. 01, Survey No. 27/2/2, Anandwalli Shiwar, Nashik, Kale Nagar 2, Behind Guruji Hospital, 422013

Dec 2025
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 90.9%.

Official RERA facts

Registration
P51600049671
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Street Lightingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Feb 2023
Floors
7
Plot / CTS / survey no.
Plot No. 01, Survey No. 27/2/2, Anandwalli Shiwar, Nashik
Planning authority
Others
Approved layout land
378.48 sq.m
Land for this registration
378.48 sq.m
Permissible built-up area
1,210.98 sq.m
Registered office
Laxminarayan Bunglow
Plot boundaries
North
Open Space
South
Survey No 27-2-4
East
Survey No 27 Part
West
Colony Road
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • HDFC BANK โ€” 52822
    IFSC HDFC0004663
    Anandwalli, Nashik

Commencement Certificate documents

  • Commencement Certificate.pdf

Buyer community

Connect with other buyers and owners of Laxminarayan Harmony โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Laxminarayan Harmony. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.