Indu ParkMahaRERA P51600049869
Plot No 53 S. No. 905/1/2/3A, Eknath Nagar, 422009
- Possession delayed ~2 yrs. Originally promised Mar 2024, now proposed Mar 2026 per the RERA filing.
- Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P51600049869
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2026originally March 2024
- Construction
- 90.9% complete
- Units sold
- 14 of 24
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EXT51600019848Revised to March 2025
The project is ready for application for OC, we have completed 70% project compliances for OC and we will apply for OC on or before 31-03-2025. To complete the of balance finishing work and to take water connection at site. We seek a further extension of one year i.e. up to 31-03-2025 to complete work and obtain an Occupation Certificate for the project. We request you to kindly extend the project completion date to 31-03-2025.
- EA04062501444Revised to March 2026
we have completed 85% project and we will get OC on or before 30-03-2026. To complete the of balance finishing work and to take water connection at site. We seek a further extension of one year i.e. up to 30-03-2026 to complete work and obtain an Occupation Certificate for the project. We request you to kindly extend the project completion date to 30-03-2026., The reason for delay in project completion is due to labour constraint due to this work is not completed on time., We have taken a approval from all the allottees for the extension and the letter of Format B is uploaded.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2023
- Floors
- 8
- Unit mix
- 22 res ยท 2 comm
- Architect
- Mahesh Jangid
- Plot / CTS / survey no.
- Plot No 53 S. No. 905/1/2/3A
- Planning authority
- Nashik Municipal Corporation
- Approved layout land
- 656.1 sq.m
- Land for this registration
- 656.1 sq.m
- Permissible built-up area
- 2,175.05 sq.m
- Registered office
- KRISHNAI GALAXY APARTMENT
- North
- Part of S No 905
- South
- Plot No 54
- East
- S No 906
- West
- 18 Meter DP Road
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- HDFC BANK โ 49268IFSC HDFC0000878Nashik
Commencement Certificate documents
- commencement_compressed.pdf
Buyer community
Connect with other buyers and owners of Indu Park โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Indu Park. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.