PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Padma Vishwa MangalamMahaRERA P51600051326

by Mangalmurti Builders

65/1/2,65/1/3,72/1,72/2/4 Plot No 26D, Navshya Ganpati, Sector C, 422013

Mar 2026
Possession
88.6%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 88.6%.

Official RERA facts

Registration
P51600051326
Status
New
Stage
Certificate Signed
Possession
March 2026
Construction
88.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Jun 2023
Floors
8
Plot / CTS / survey no.
65/1/2,65/1/3,72/1,72/2/4 Plot No 26D
Planning authority
Others
Approved layout land
402 sq.m
Land for this registration
402 sq.m
Permissible built-up area
1,255.87 sq.m
Registered office
Siddhi Pooja Regency
Plot boundaries
North
Plot no 26C
South
Plot No 26H
East
6 meter wide colony road
West
Adjoining Survey no 59
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • BANK OF BARODA โ€” 6860
    IFSC BARB0GANNAS
    Gangapur Road, Nashik

Commencement Certificate documents

  • Navshya ganpati mangalam commencement certificate_compressed.pdf
  • revised commencement.pdf

Buyer community

Connect with other buyers and owners of Padma Vishwa Mangalam โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Padma Vishwa Mangalam. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.