GOKUL 7MahaRERA P51600051838
PLOT NO.05+06, S. NO. 93/1/B, SAMBHAJI NAGAR, 422012
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P51600051838
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jul 2023
- Floors
- 7
- Plot / CTS / survey no.
- PLOT NO.05+06, S. NO. 93/1/B
- Planning authority
- Others
- Approved layout land
- 675.75 sq.m
- Land for this registration
- 675.75 sq.m
- Permissible built-up area
- 2,159.34 sq.m
- Registered office
- SARVADNYA BUNGLOW
- North
- ADJACENT S NO 93-P
- South
- ADJACENT PLOT NO 07
- East
- OPEN SPACE
- West
- 9 METER WIDE ROAD
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- CITY UNION BANK LIMITED โ 27973IFSC CIUB0000182GROUND FLOOR, AMARANAND HOUSE, K N MORE MARG, PATIL LANE NO 4, OFF COLLEGE ROAD, NASHIK - 422005
Commencement Certificate documents
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of GOKUL 7 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching GOKUL 7. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.