HARIOM ENCLAVEMahaRERA P51600051993

by HARIOM GROUP

PLOT NO. 53+54 OF S.NO./G.NO. 180/1B 2C 1 2 18/1A 1A 1 1/1 2 18/1A/1C/53+54 NASHIK SHIWAR, KSHIRSAGAR COLONY, 422003

Mar 2026
Possession
77.3%
Built
0
Complaints
14
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 77.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2026 per the RERA filing.

Official RERA facts

Registration
P51600051993
Status
New
Stage
Certificate Signed
Possession
March 2026
Construction
77.3% complete
Units sold
8 of 14

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2023
Floors
8
Unit mix
14 res ยท 0 comm
Architect
SURESH N PATEL NARSIH MAWANI
Plot / CTS / survey no.
PLOT NO. 53+54 OF S.NO./G.NO. 180/1B 2C 1 2 18/1A 1A 1 1/1 2 18/1A/1C/53+54 NASHIK SHIWAR
Planning authority
NASHIK MUNICIPAL CORPORATION
Approved layout land
560.75 sq.m
Land for this registration
560.75 sq.m
Permissible built-up area
1,667 sq.m
Registered office
S NO. 207/6C
Plot boundaries
North
9 M W ROAD
South
PLOT NO 55
East
PLOT NO 10
West
9 M W ROAD
Parking
14 four-wheeler32 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • KOTAK MAHINDRA BANK LIMITED โ€” 85178
    IFSC KKBK0001913
    PANCHAVATI NASHIK

Commencement Certificate documents

  • COMMENCEMENT CERTIFICATC Enclave_compressed.pdf

Buyer community

Connect with other buyers and owners of HARIOM ENCLAVE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HARIOM ENCLAVE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.