Feriha HeightsMahaRERA P51600055909

by Aroma Developers

Plot No- 20+21, Survey No- 113/3/11 to 16/21 to 23, Wadala, Shiwar, 422007

Mar 2027
Possession
49.1%
Built
0
Complaints
28
Units
High risk
  • Behind schedule. Possession is due Mar 2027 but construction is only at 49.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51600055909
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
49.1% complete
Units sold
13 of 28

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA29052621159Revised to March 2027

    The project completion and submission of this request have experienced delays primarily on account of procurement challenges, financial constraints, and certain site-related operational issues. These factors have impacted the overall execution timeline and resulted in a revised pace of work. However, necessary corrective measures are now being implemented to streamline procurement, strengthen financial planning, and resolve site-level bottlenecks to ensure steady progress of the remaining work. We are now actively focused on accelerating the balance construction activities and coordinating with all concerned stakeholders to ensure timely execution of pending works. Considering the current status of the project and the steps being taken to regularize and expedite progress, we kindly request an extension up to 31-03-2027 for completion of the project and to ensure compliance with all applicable regulatory requirements.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingdone
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2024
Floors
8
Unit mix
24 res ยท 4 comm
Plot / CTS / survey no.
Plot No- 20+21, Survey No- 113/3/11 to 16/21 to 23
Planning authority
Nashik Municipal Corporation
Approved layout land
530.33 sq.m
Land for this registration
530.33 sq.m
Permissible built-up area
1,658.19 sq.m
Registered office
Kailashdarshan
Plot boundaries
North
9 M W Road
South
Adj S No 113 3 P
East
Adj Plot No 22
West
9 M Wide Road
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • KOTAK MAHINDRA BANK LIMITED โ€” 85058
    IFSC KKBK0001429
    Ganges Printing Ink Building ,Gaga House, Lbs Marg, Opp Cipla Ltd, Vikhroli W, Mumbai- 400083

Commencement Certificate documents

  • commencement certificate.pdf

Buyer community

Connect with other buyers and owners of Feriha Heights โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Feriha Heights. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.