Bait E Muhammad Phase 1MahaRERA P51600077618
Survey No. 3/1/5/2 to 3/1/8/2, Wadala Shiwar, Nashik, RAHMAT NAGAR, OPP. VITTHAL RUKMINI TEMPLE, WADALA, 422006
No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P51600077618
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2029
- Construction
- 50.9% complete
- Units sold
- 57 of 120
RERA complaint record1 record
- ComplaintCC1260437813 Jul 2026Hozefa Aftab Hakim vs Onyx Constructions
Landowner
Sanjay Vinayak Khanzode
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2024
- Floors
- 6
- Unit mix
- 120 res ยท 0 comm
- Architect
- Sumit Kumath
- Plot / CTS / survey no.
- Survey No. 3/1/5/2 to 3/1/8/2, Wadala Shiwar, Nashik
- Planning authority
- Nashik Municipal Corporation
- Approved layout land
- 6,340 sq.m
- Land for this registration
- 6,340 sq.m
- Recreational open space
- 1,050.44 sq.m
- Permissible built-up area
- 7,632.26 sq.m
- Registered office
- Grand Al Khatib Restaurant Building
- North
- Proposed Phase 2 Building G and 12 Meter Road
- South
- Survey No 67
- East
- Survey No 3-1-9
- West
- Survey No 3-1-5 to 8-1
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- KOTAK MAHINDRA BANK LIMITED โ 85179IFSC KKBK0001915GR AND MEZZANINE FLOOR SHOP 1 2 AND OFFI BEARING 12 SHREEJI BIZZ WORLD OPP CAMEL HOUSE NASHIK 422011
Commencement Certificate documents
- Commencement Certificate.pdf
- Commencement Certificate.pdf
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of Bait E Muhammad Phase 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Bait E Muhammad Phase 1. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.