Under construction

PALAVA REGALIA A to F

by Palava Dwellers Private Limited

96/2B PT, 99 PT, 98/1 PT, Kalyan, 421202

Caution
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 78.2%.

Official RERA facts

Registration
P51700000390
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
78.2% complete
Units sold
0 of 0

RERA complaint record2 records

  • ComplaintCC00600000039790923 Oct 2023
    Macrotech Developers Ltd. vs REEMA BIJAY GOUD
    order CC006000000397909 -.pdf on MahaRERA
  • Misc. applicationCC00600000039790923 Oct 2023
    Macrotech Developers Ltd. vs REEMA BIJAY GOUD

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting90%
Street Lighting75%
Community Buildings10%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcnt85%
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space95%
Open Parking70%
Woodland Park50%
Temple50%
Sports Complex20%
Clubhouse10%

Building & registration

RERA registered
Jul 2017
Floors
18

Buyer community

Connect with other buyers and owners of PALAVA REGALIA A to F โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PALAVA REGALIA A to F. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.