Under construction

PALAVA URBANO D AND E

by Lodha Developers Limited

53/5 PT 144/3 PT 144/4 PT, Kalyan, 421202

High risk
  • Possession date passed. The proposed possession date (Oct 2022) has passed with construction at 78.9%.
  • Promised amenities not started. Sports / Jogging is at 0% build with possession due Oct 2022 per the RERA filing.

Official RERA facts

Registration
P51700000577
Status
Ongoing
Stage
Certificate Signed
Possession
October 2022
Construction
78.9% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parking90%
ClubHousenot started
Sports Complexnot started
TEMPLEnot started

Building & registration

RERA registered
Jul 2017
Floors
18

Buyer community

Connect with other buyers and owners of PALAVA URBANO D AND E โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PALAVA URBANO D AND E. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.