๐Ÿ—๏ธ
Under construction

PALAVA CLUSTER 2-06 - A - G, I - N

by Lodha Developers Limited

144/6PT, 37/1APT, 37/2APT, 40/2PT, 143/2PT, 143/3PT, 38/2PT, 38/5PT, 37/1B, , Kalyan, 421202

Caution
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 78.2%.

Official RERA facts

Registration
P51700000802
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022
Construction
78.2% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone
Club Housedone
Sports Complexdone
Templedone

Building & registration

RERA registered
Jul 2017
Floors
18

Buyer community

Connect with other buyers and owners of PALAVA CLUSTER 2-06 - A - G, I - N โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PALAVA CLUSTER 2-06 - A - G, I - N. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.