Under construction

Balaji Symphony phase 3

by Vinay Agrawal

173-0, Thane, 410206

High risk
  • Possession delayed ~7 yrs. Originally promised Jun 2021, now proposed Jun 2028 per the RERA filing.

Official RERA facts

Registration
P51700000973
Status
Ongoing
Stage
Certificate Signed
Possession
June 2028originally June 2021
Construction
100% complete
Units sold
430 of 430

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jul 2017
Floors
36
Unit mix
430 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Balaji Symphony phase 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Balaji Symphony phase 3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.