Under construction

LODHA AMARA - TOWER 26, 27, 28, 30, 34, 35

by LODHA DEVELOPERS LIMITED

64/3,64/7,65/2,65/3,65/4,65/5, 68/3,68/4,68/5,69/2,69/6,70/1,70/2,70/3,70/4,72/2,72/3,73/1, Thane, 400607

High risk
  • 18 RERA complaints. 18 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 78.2%.
Thane (Ghodbunder belt)Mid-income

A full city of its own โ€” lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700001031
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
78.2% complete
Units sold
0 of 0

RERA complaint record18 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting60%
Street Lighting40%
Community Buildings95%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Space70%
Open Parkingnot started
Closed Parkings40%

Building & registration

RERA registered
Jul 2017
Floors
30

Buyer community

Connect with other buyers and owners of LODHA AMARA - TOWER 26, 27, 28, 30, 34, 35 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching LODHA AMARA - TOWER 26, 27, 28, 30, 34, 35. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.