MARATHON NEXTOWN SAPPHIRE

by MARATHON ENER-GEN LLP

140, 141/2, 141/1, 142/3, 220/1B, 220/2, 220/5, 232, OFF KALYAN SHIL ROAD, 421201

Jun 2024
Possession
85.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2021, now proposed Jun 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 85.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2024 per the RERA filing.

Official RERA facts

Registration
P51700001265
Status
Ongoing
Stage
Certificate Signed
Possession
June 2024originally December 2021
Construction
85.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths98%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station98%

Building & registration

RERA registered
Jul 2017
Floors
17

Buyer community

Connect with other buyers and owners of MARATHON NEXTOWN SAPPHIRE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MARATHON NEXTOWN SAPPHIRE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.