PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Regency Sarvam Phase - 8

by REGENCY NIRMAN LTD

Village Manda Survey No. 42/1, 42/2, 42/3, 42/4/1,42/4/2, 42/5, 42/6, 47/1, 50/1/B, 50/2, 220/1, 251, Titwala, 421605

Aug 2018
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Aug 2018) has passed with construction at 90.9%.

Official RERA facts

Registration
P51700002824
Status
Ongoing
Stage
Certificate Signed
Possession
August 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
18

Buyer community

Connect with other buyers and owners of Regency Sarvam Phase - 8 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Regency Sarvam Phase - 8. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.