Under construction

ATLANTA EDENWORLD PHASE I

by SAI BALAJI DEVELOPER

67H/69H/80H/81, Thane, 421302

Caution
  • Possession date passed. The proposed possession date (Nov 2018) has passed with construction at 90.4%.

Official RERA facts

Registration
P51700003328
Status
Ongoing
Stage
Certificate Signed
Possession
November 2018originally December 2017
Construction
90.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply97%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting50%
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Energy managemcnt95%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Aug 2017
Floors
14
Public authority
Bhiwandi Municipal Corporation

Buyer community

Connect with other buyers and owners of ATLANTA EDENWORLD PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ATLANTA EDENWORLD PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.