Under construction

Riverwood Park Building No. 4

by Shree Khidkaleshwar Property Developers Pvt. Ltd.

26/5, 28/1, 53, all in parts, Thane, 421204

High risk
  • Possession date passed. The proposed possession date (Oct 2023) has passed with construction at 94.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2023 per the RERA filing.

Official RERA facts

Registration
P51700004003
Status
Ongoing
Stage
Certificate Signed
Possession
October 2023originally October 2022
Construction
94.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving station95%
Club House and Swimming pool30%

Building & registration

RERA registered
Aug 2017
Floors
29

Buyer community

Connect with other buyers and owners of Riverwood Park Building No. 4 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Riverwood Park Building No. 4. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.