Under construction

SAHAJEEVAN

by Shree Khodiyar Builders and Developers

H1 And H2 Survey No 39P and Survey No 41 P, Ambarnath, 421501

High risk
  • Possession delayed ~2 yrs. Originally promised May 2019, now proposed Nov 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Nov 2020) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2020 per the RERA filing.

Official RERA facts

Registration
P51700004182
Status
Ongoing
Stage
Certificate Signed
Possession
November 2020originally May 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of SAHAJEEVAN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAHAJEEVAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.