High risk
  • Possession delayed ~2 yrs. Originally promised Apr 2019, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 99.1%.

Official RERA facts

Registration
P51700004679
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally April 2019
Construction
99.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths85%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains90%
Landscaping & Tree Planting35%
Street Lightingnot started
Community Buildings30%
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting90%
Energy managemcntnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Space20%
Open Parking80%

Building & registration

RERA registered
Aug 2017
Floors
20

Buyer community

Connect with other buyers and owners of ARIHANT AAROHI PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ARIHANT AAROHI PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.