Under construction

Paramount B

by Kalpataru Homes Private Limited

S.NO. 114/8-Part,114/4-Part,114/9A-Part,115/9-Part,115/12-Part of village Majiwade, Thane, 400608

High risk
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 93.4%.
  • Promised amenities not started. Swimming Pool, Gymnasium, Clubhouse are at 0% build with possession due Jun 2025 per the RERA filing.
Thane (Ghodbunder belt)Mid-income

A full city of its own โ€” lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700004741
Status
Ongoing
Stage
Certificate Signed
Possession
June 2025
Construction
93.4% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsdone
Water Supplynot started
Water Supply50%
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)78%
Sewerage (Chamber, Lines, Septic Tank , STP)78%
Storm Water Drains22%
Storm Water Drains22%
Landscaping & Tree Planting4%
Landscaping & Tree Planting13%
Landscaping & Tree Planting4%
Street Lightingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Water60%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal95%
Solid Waste Management And Disposal90%
Solid Waste Management And Disposal90%
Water conservation /Rain water harvesting67%
Water conservation /Rain water harvesting67%
Energy managemcntnot started
Energy managemcnt20%
Energy managemcntnot started
Fire protection and fire safety requirements90%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station79%
Electrical meter room, sub-station, receiving station55%
Electrical meter room, sub-station, receiving station38%
Aggregate area of recreational Open Spacenot started
Aggregate area of recreational Open Space20%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Open Parkingnot started
2 Nos of Common Basement1%
2 Nos of Common Basement66%
Club House, Fitness Centre, Swimming Pool and other Recreational Areasnot started
3 Nos of Common Podiumnot started
3 Nos of Common Podium63%
Club House, Fitness Centre, Swimming Pool and other Recreational Areasnot started
Club House, Fitness Centre, Swimming Pool and other Recreational Areas37%
2 Nos of Common Basement1%
3 Nos of Common Podiumnot started

Building & registration

RERA registered
Aug 2017
Floors
40
Architect
M/S Entech Consultant (Form 1 & Form 4)

Buyer community

Connect with other buyers and owners of Paramount B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Paramount B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.