PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

New Kirtikar Proposed

by New Kirtikar Proposed

123/A/1,372, Thane, 400602

High risk
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 49.5%.
Thane (Ghodbunder belt)Mid-income

A full city of its own โ€” lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700004963
Status
Ongoing
Stage
Certificate Signed
Possession
July 2026
Construction
49.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
lift50%
Solar water50%

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of New Kirtikar Proposed โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching New Kirtikar Proposed. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.