Under construction

Airoli Co op housing soc Ltd.

by Jayant Shashikant Parikh

1, Thane, 400708

Caution
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P51700006609
Status
Ongoing
Stage
Certificate Signed
Possession
March 2031
Construction
58.1% complete
Units sold
88 of 236

RERA complaint record6 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvesting70%
Fire protection and fire safety requirements55%
Electrical meter room, sub-station, receiving station55%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
32
Unit mix
236 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Airoli Co op housing soc Ltd. โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Airoli Co op housing soc Ltd.. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.