All RERA projects
๐๏ธ
Dec 2027
Possession
104.7%
Built
1
Complaints
64
Units
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2022, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P51700006631
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2022
- Construction
- 104.7% complete
- Units sold
- 64 of 64
RERA complaint record1 record
- ComplaintCC00600000019899320 Nov 2021Firoz Shaikh vs Shakeel Shaikh
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains60%
Landscaping & Tree Planting60%
Solid Waste Management And Disposal60%
Water conservation /Rain water harvesting60%
Energy managemcnt60%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station60%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 9
- Unit mix
- 64 res ยท 0 comm
Buyer community
Connect with other buyers and owners of K K RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching K K RESIDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.