Under construction

SAI KANISHK PHASE I

by Om Sai Infra & Om Sai Group

5/5B,9, Thane, 400612

High risk
  • 11 RERA complaints. 11 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (May 2018) has passed with construction at 90%.

Official RERA facts

Registration
P51700006847
Status
Ongoing
Stage
Certificate Signed
Possession
May 2018originally December 2017
Construction
90% complete
Units sold
0 of 0

RERA complaint record11 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drains50%
Landscaping & Tree Planting70%
Community Buildings50%
Water conservation /Rain water harvesting30%
Energy managemcnt90%
Electrical meter room, sub-station, receiving station30%
Aggregate area of recreational Open Space70%
Open Parking50%

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of SAI KANISHK PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI KANISHK PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.