AKSHAR ALVARIO

by THALIA AKSHAR DEVELOPERS

PLOT NO. 76, Thane, 400706

Caution
  • Possession date passed. The proposed possession date (Nov 2018) has passed with construction at 87.6%.
Navi Mumbai (Vashi–Nerul)Mid-income

Planned-city order — wide roads, node markets, established social infra.

Growth drivers:
Atal Setu (MTHL), metro lines, the upcoming Navi Mumbai airport.
Who buys here:
Professionals wanting planned-city living with airport-corridor upside.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700006864
Status
Ongoing
Stage
Certificate Signed
Possession
November 2018
Construction
87.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Plantingdone
Community Buildings40%
Water conservation /Rain water harvesting90%
Energy managemcntnot started
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving station30%

Building & registration

RERA registered
Aug 2017
Floors
16

Buyer community

Connect with other buyers and owners of AKSHAR ALVARIO — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching AKSHAR ALVARIO. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.