Under construction

PARKWOODS D5

by Aniline Construction Company Private Limited

165/1Apt, 166/6Apt, 166/8Apt, D-Mart, Kavesar, 400615

Dec 2026
Possession
65.1%
Built
3
Complaints
420
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700007024
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally March 2026
Construction
65.1% complete
Units sold
420 of 420

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
62
Unit mix
420 res ยท 0 comm
Architect
Saakaar

Buyer community

Connect with other buyers and owners of PARKWOODS D5 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PARKWOODS D5. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.