All RERA projects
๐๏ธ
Dec 2020
Possession
75%
Built
1
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 75%.
Official RERA facts
- Registration
- P51700007118
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2020
- Construction
- 75% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00600000020969322 Jan 2022Mr Chetan Barku Solse & 9 others vs M/S Shri. Balaji ConstructionOrder of Chetan Solse (1).pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths80%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Planting80%
Street Lighting50%
Community Buildings50%
Water conservation /Rain water harvesting50%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space75%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 9
Buyer community
Connect with other buyers and owners of KRISHNA HERITAGE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching KRISHNA HERITAGE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.