Under construction

DURGA IMPERIAL

by G K MALI & C K MALI

Survey No8, Hissa No 3 CTS No 132, Kalyan, 421306

High risk
  • Possession delayed ~3 yrs. Originally promised Oct 2023, now proposed Oct 2026 per the RERA filing.
  • Behind schedule. Possession is due Oct 2026 but construction is only at 44.3%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Oct 2026 per the RERA filing.
Kalyan–DombivliValue

Central-line volume market — affordable towers around busy junctions.

Growth drivers:
Metro 5, ring-road plans, the region's most accessible pricing.
Who buys here:
Budget-first buyers who commute the central line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700007962
Status
Ongoing
Stage
Certificate Signed
Possession
October 2026originally October 2023
Construction
44.3% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC00600000030343228 Nov 2022
    Dhananjay Ashok Tawade vs G K MALI & C K MALI
    33o.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths25%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting20%
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
31
Public authority
KALYAN DOMBIVILI MUNCIPAL CORPORATION - KDMC

Buyer community

Connect with other buyers and owners of DURGA IMPERIAL — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching DURGA IMPERIAL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.