All RERA projects
๐๏ธ
Under construction
VIRAT AANGAN BUILDING NO 1
SURVEY NO 229 HISSA NO 6, GANESH NAGAR, 421605
Dec 2019
Possession
72.7%
Built
0
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 72.7%.
Official RERA facts
- Registration
- P51700007977
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2019
- Construction
- 72.7% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone
SOCIETY OFFICEdone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 14
Buyer community
Connect with other buyers and owners of VIRAT AANGAN BUILDING NO 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VIRAT AANGAN BUILDING NO 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.