  • 12 RERA complaints. 12 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 90.9%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2018 per the RERA filing.

Official RERA facts

Registration
P51700008298
Status
Ongoing
Stage
Certificate Signed
Possession
June 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record12 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Aug 2017
Floors
18

Buyer community

Connect with other buyers and owners of Sunrise Glory - Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sunrise Glory - Phase I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.