Under construction
SANIYA HEIGHTS
PLOT NO. 14, 15, 19, 20, 21, 22, 23, 24 CTS NO. 4037P, 4039P, S. NO. 32/2, 36/2,36/3, 37, 38, 74/3,, Bhiwandi, 421302
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Sept 2026 per the RERA filing.
- 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
Official RERA facts
- Registration
- P51700008927
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2026originally December 2021
- Construction
- 75.5% complete
- Units sold
- 132 of 132
RERA complaint record7 records
- ComplaintCC1260101125 Feb 2026Nadeem Ahmad Lal Mohammad Ansari vs MOONSHINE REALTORS PVT LTD
- ComplaintCC0060000004291408 Feb 2024Ayub Suleman Khan vs Moonshine Realtors Private LimitedFO P51700008927 MOONSHINE REALTORS PVT LTD.pdf on MahaRERA
- ComplaintCC00600000039740614 Dec 2023Ayub Suleman Khan vs Moonshine Realtors Pvt. LtdFO P51700008927 MOONSHINE REALTORS PVT LTD.pdf on MahaRERA
- ComplaintCC00600000040840514 Dec 2023Rashid Mohammed Hussein Bhopali vs Moonshine Realtors Pvt. LtdFO P51700008927 MOONSHINE REALTORS PVT LTD.pdf on MahaRERA
- ComplaintCC00600000037497210 Apr 2023Mohd Ashrafali Mohammad Yusuf Shah vs Moonshine Realtors Pvt. LtdFO P51700008927 MOONSHINE REALTORS PVT LTD.pdf on MahaRERA
- ComplaintCC00600000019631621 Mar 2021Abdul Malik Usmani vs Moonshine Realtors Pvt Ltd196316 warrant_compressed.pdf on MahaRERA
- Misc. applicationCC00600000019631621 Mar 2021Abdul Malik Usmani vs Moonshine Realtors Pvt Ltd196316 warrant_compressed.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drains20%
Landscaping & Tree Planting25%
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 18
- Unit mix
- 124 res ยท 8 comm
- Architect
- ALIM AK FOUZI
Buyer community
Connect with other buyers and owners of SANIYA HEIGHTS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SANIYA HEIGHTS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.