PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ORCHID ARCADE

by SWASTIK ANMOL BUILDERS AND DEVELOPERS

PLOT NO 6, VASHI, NAVI MUMBAI, 400703

Dec 2028
Possession
82.7%
Built
0
Complaints
37
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Jun 2024, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51700010098
Status
Ongoing
Stage
Certificate Signed
Possession
December 2028originally June 2024
Construction
82.7% complete
Units sold
6 of 37

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements10%
Electrical meter room, sub-station, receiving station40%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
17
Unit mix
29 res ยท 8 comm
Architect
DIMENSIONS ARCHITECTS PVT LTD

Buyer community

Connect with other buyers and owners of ORCHID ARCADE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ORCHID ARCADE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.