PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SADASHIV PURAM

by SATYABHAMA DEVELOPERS

GUT NO 10 CTS 9285, Ambarnath(M Cl), 421501

Mar 2018
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2018) has passed with construction at 90.9%.
Ambernath / BadlapurValue

The value frontier beyond Kalyan โ€” low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700010168
Status
Ongoing
Stage
Certificate Signed
Possession
March 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Community Buildingsdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of SADASHIV PURAM โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SADASHIV PURAM. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.