Under construction

KAVYA PARK

by SHREE CONSTRUCTION COMPANY

S NO 29 AT BORIWADE, GHODBUNDER ROAD, THANE WEST, THANE, 400615

Jun 2027
Possession
53.6%
Built
17
Complaints
173
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Jun 2027 per the RERA filing.
  • 17 RERA complaints. 17 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51700010575
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally June 2021
Construction
53.6% complete
Units sold
141 of 173

RERA complaint record17 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
31
Unit mix
143 res ยท 30 comm
Architect
ARCHIT CONSULTANTS

Buyer community

Connect with other buyers and owners of KAVYA PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KAVYA PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.