Under construction

Goldcrest Residency - Phase 2

by SAVITA HOMEMAKERS LLP

Plot No 7, Sector 11, Ghansoli, Navi Mumbai, GHANSOLI, 400701

Mar 2027
Possession
97.3%
Built
115
Complaints
316
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Mar 2027 per the RERA filing.
  • 115 RERA complaints. 115 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P51700010579
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally June 2021
Construction
97.3% complete
Units sold
316 of 316

RERA complaint record115 records

Complaint data not yet synced for this project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths96%
Water Supply88%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting85%
Street Lighting93%
Solid Waste Management And Disposal97%
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Fire protection and fire safety requirements91%
Electrical meter room, sub-station, receiving station93%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
30
Unit mix
316 res ยท 0 comm
Architect
Soyuz Talib

Buyer community

Connect with other buyers and owners of Goldcrest Residency - Phase 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Goldcrest Residency - Phase 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.