All RERA projects
๐๏ธ
Under construction
INDRAYANI
Survey No. 6, Hissa No. 1, 2 and 3, Manda, 421605
Oct 2026
Possession
74.5%
Built
0
Complaints
70
Units
High risk
- Possession delayed ~8 yrs. Originally promised Oct 2018, now proposed Oct 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700010665
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2026originally October 2018
- Construction
- 74.5% complete
- Units sold
- 49 of 70
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 10
- Unit mix
- 64 res ยท 6 comm
Buyer community
Connect with other buyers and owners of INDRAYANI โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching INDRAYANI. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.