Under construction

FALCO PEARLSHIRE

by AANYA RESIDENCES

37/3A P, Ambivali Tarf Chon, 421102

Dec 2027
Possession
39.1%
Built
4
Complaints
83
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2022, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51700011065
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2022
Construction
39.1% complete
Units sold
50 of 83

RERA complaint record4 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
13
Unit mix
82 res ยท 1 comm
Architect
RASHTRAPAL JADHAV

Buyer community

Connect with other buyers and owners of FALCO PEARLSHIRE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching FALCO PEARLSHIRE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.