Under construction
UMA RESIDENCY, PHASE I
Survey No. 22 , Hissa No 2 and 6, NA, 421601
Aug 2026
Possession
48.8%
Built
0
Complaints
120
Units
High risk
- Possession delayed ~5 yrs. Originally promised Jun 2021, now proposed Aug 2026 per the RERA filing.
- Behind schedule. Possession is due Aug 2026 but construction is only at 48.8%.
Official RERA facts
- Registration
- P51700011302
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2026originally June 2021
- Construction
- 48.8% complete
- Units sold
- 31 of 120
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths95%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains95%
Landscaping & Tree Planting95%
Water conservation /Rain water harvesting80%
Energy managemcnt75%
Electrical meter room, sub-station, receiving station95%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 5
- Unit mix
- 120 res ยท 0 comm
- Architect
- Parth Consultant and Town Planners
Buyer community
Connect with other buyers and owners of UMA RESIDENCY, PHASE I โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching UMA RESIDENCY, PHASE I. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.