Under construction

Shantiniketan Wing B4

by Anmol Associates

Sr No. 38,39,40,236,238,259, Kalyan, 421201

High risk
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 75%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2019 per the RERA filing.

Official RERA facts

Registration
P51700011429
Status
Ongoing
Stage
Certificate Signed
Possession
December 2019
Construction
75% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths45%
Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains55%
Landscaping & Tree Plantingnot started
Street Lighting10%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting10%
Energy managemcnt30%
Fire protection and fire safety requirements45%
Electrical meter room, sub-station, receiving station30%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
11

Buyer community

Connect with other buyers and owners of Shantiniketan Wing B4 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shantiniketan Wing B4. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.