PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

MAULI KRUPA

by VIGHNESH CONSTRUCTIONS

PLOT NO 22 SECTOR 15, NAVI MUMBAI, 400701

Dec 2026
Possession
86.4%
Built
0
Complaints
18
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Aug 2018, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700011488
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally August 2018
Construction
86.4% complete
Units sold
5 of 18

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting50%
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
6
Unit mix
16 res ยท 2 comm

Buyer community

Connect with other buyers and owners of MAULI KRUPA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAULI KRUPA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.