Under construction

PALAVA MILANO E, F

by Palava Dwellers Private Limited

36/2 pt, 141/3 pt, 36/3 pt, 36/5 pt, -, 421202

Mar 2023
Possession
72.7%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 72.7%.
  • Promised amenities not started. Sports / Jogging is at 0% build with possession due Mar 2023 per the RERA filing.

Official RERA facts

Registration
P51700011629
Status
New
Stage
Certificate Signed
Possession
March 2023
Construction
72.7% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone
Templenot started
Sports Complexnot started
Club Housenot started
Closing Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
18

Buyer community

Connect with other buyers and owners of PALAVA MILANO E, F โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PALAVA MILANO E, F. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.