Under construction

Kalika Heights Phase II

by Sanjay shreenath pandey

F.P.No 366, PANCHPAKHADI, 400061

Jun 2027
Possession
79.8%
Built
0
Complaints
56
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2019, now proposed Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51700011655
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally December 2019
Construction
79.8% complete
Units sold
26 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains70%
Landscaping & Tree Planting30%
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station70%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
23
Unit mix
56 res ยท 0 comm
Architect
Nilesh Sawant

Buyer community

Connect with other buyers and owners of Kalika Heights Phase II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kalika Heights Phase II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.