PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Durahomes Builders and developers pvt ltd

by Arshad Ahmed Siddiqui

19,20,21,22,23,81/2,81/5,82/3,83/1,103,107, chavindra, 421302

Jul 2028
Possession
44.5%
Built
0
Complaints
0
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700012518
Status
Ongoing
Stage
Certificate Signed
Possession
July 2028
Construction
44.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2017
Floors
2

Buyer community

Connect with other buyers and owners of Durahomes Builders and developers pvt ltd โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Durahomes Builders and developers pvt ltd. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.